| title: "Milestone Schedule" |
| linkTitle: "Milestone Schedule" |
| |
| --- |
| |
| |
| On a six week cadence aligned with Chromium, Skia cuts milestone branches. |
| Clients wishing to stay on a relatively stable level of Skia often utilize these |
| branches. |
| |
| On the branch date, a healthy level of Skia near HEAD is chosen. After this |
| point, for the next six weeks, only high priority fixes are checked into the branch. |
| After the six week period, when another branch is cut, only critical (typically |
| security) fixes will be committed to any previous branch. |
| |
| Skia 2020 schedule: |
| |
| Milestone | Branch Date (beginning of day) |
| ----------|------------------------------- |
| 81 | 01/30/20 |
| 82 | 03/12/20 |
| 83 | 04/02/20* |
| 84 | 05/14/20 |
| 85 | 06/25/20 |
| 86 | 08/20/20 |
| 87 | 10/01/20 |
| 88 | 11/12/20 |
| |
| Note that 82 was abandoned by Chromium and 83 schedule moved in due to COVID-19 impact. |
| Skia is maintaining 82 for our customers. Future dates are subject to change. |
| |
| The current milestone is included in the headers in |
| [SkMilestone.h](https://skia.googlesource.com/skia/+/main/include/core/SkMilestone.h). |
| |